Timeline: Construction of the New Cable System

  • February 2015 – June 2016: Construction at Canal Street and Salem Harbor Substations for new cable termination structures and equipment

  • February 2015 – December 2015: Ductbank and manhole installation and temporary pavement restoration

  • November 2015 – May 2016: Cable installation, pulling, splicing, and testing

  • October 2015 – June 2016: Cutover and energizing of new S and T cables

  • Spring 2016 : Removal of existing S and T cables

  • March 2016 – June 2016: Final restoration of new cable route